100 MW Wind Project in Qorao’zak District, Republic of Karakalpakstan, Republic of Uzbekistan (the “Project”)
In response to the Request for Qualifications (RfQ) for the Project sent to Applicants on 11th September 2020, the parties listed below have submitted compliant Statements of Qualifications at the time of the deadline on 10 November 2020, 12:00 noon Tashkent time for electronic submissions, together with the evidence of the shipment of their hard copy submissions.
On the basis of foregoing, the Ministry of Energy (MOE), the Ministry of Investments and Foreign Trade (MIFT), JSC National Electric Grid of Uzbekistan (NEGU) and the Public-Private Partnership Development Agency (PPPDA) under the Ministry of Finance have determined the following list of Prequalified Bidders (in alphabet order) to receive a Request for Proposals (RfP).
# |
Prequalified Bidders |
1 |
Abu Dhabi Future Energy Company – Masdar |
2 |
China Hua Neng Group Hong Kong Limited |
3 |
China Power International Holding Limited |
4 |
China Three Gorges South Asia Investment Limited |
5 |
Consortium of AC Renewables International Pte Limited and UPC Renewables Limited |
6 |
Consortium of Yildizlar Construction and Trade Inc., Mingyang Smart Energy Group, Energo Pro AS, and Ipak Yo’li Financial Advisory LLC |
7 |
Enel Green Power SpA |
8 |
International Company for Water and Power Projects (ACWA Power) |
9 |
Korea Electric Power Corporation (KEPCO) |
10 |
Total Eren S.A. |
11 |
Toyota Tsusho Corporation |
12 |
Voltalia |
The Government of Uzbekistan acknowledges the contribution of the Government of Japan and EBRD shareholders, as the donors of the technical assistance supporting the Project.